Article 66 Year-ahead individual grid models
United Kingdom
Each TSO shall determine a year-ahead individual grid model for each of the scenarios developed pursuant to Article 65, using its best estimates of the variables defined in Article 65(1). F1...
When defining its year-ahead individual grid model, each TSO shall:
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
balance for each scenario the sum of:
- (i)
net exchanges on AC lines;
- (ii)
estimated power flows on HVDC systems;
- (iii)
load, including an estimation of losses; and
- (iv)
generation.
Each TSO shall include in its year-ahead individual grid models the aggregated power outputs for power generating facilities connected to distribution systems. Those aggregated power outputs shall:
be consistent with the structural data provided in accordance with the requirements of Articles F3... 43, 45 and 48;
be consistent with the scenarios developed in accordance with Article 65; and
distinguish the type of primary energy source.
Annotations
Textual amendments
- F1
Words in Art. 66(1) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 50(2) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
- F2
Art. 66(2)(a) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 50(3) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Word in Art. 66(3)(a) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 50(4) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)