Article 90 Treatment of relevant assets located in a distribution system or in a closed distribution system
United Kingdom
1.
Each TSO shall coordinate with the DSO the outage planning of internal relevant assets connected to its distribution system.
2.
Each TSO shall coordinate with the CDSO the outage planning of internal relevant assets connected to its closed distribution system.
Notes on Chapter 1
Textual amendments
- F1
Words in Pt. 3 Title 3 Ch. 1 substituted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 57 (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)