Article 26 Re-energisation procedure
United Kingdom
1.
The re-energisation procedure of the restoration plan shall contain a set of measures allowing the TSO to apply:
(a)
a top-down re-energisation strategy; and
(b)
a bottom-up re-energisation strategy.
2.
Regarding the bottom-up re-energisation strategy, the re-energisation procedure shall contain at least measures for:
(a)
managing voltage and frequency deviations due to re-energisation;
(b)
monitoring and managing island operation; and
(c)
resynchronising island operation areas.