Division 8.1.10.1.1 Scope and frequency
United Kingdom
For all FID analyzers, the FID shall be calibrated upon initial installation. The calibration shall be repeated as needed using good engineering judgment. The following steps shall be performed for a FID that measures HC:
- (a)
A FID's response to various hydrocarbons shall be optimized after initial analyzer installation and after major maintenance. FID response to propylene and toluene shall be between 0,9 and 1,1 relative to propane;
- (b)
A FID's methane (CH4) response factor shall be determined after initial analyzer installation and after major maintenance as described in point 8.1.10.1.4;
- (c)
Methane (CH4) response shall be verified within 185 days before testing.