Article 24A Accredited FIT installationsF1
Paragraph (2) applies where—
a specified event has happened in relation to a FIT licensee (“A”);
immediately before the event a FIT generator (“P”), or P’s nominated recipient, was entitled to receive FIT payments from A in respect of an accredited FIT installation; and
another FIT licensee (“B”)—
(where B is a mandatory FIT licensee) has received a notification from P that P is to transfer to B for FIT payments in respect of an accredited FIT installation; or
(where B is a voluntary FIT licensee) has received a request from P to transfer to B for FIT payments in respect of that installation and B has accepted that request in writing to P.
Where this paragraph applies—
the Authority may give a direction to B (“a continuity of FIT payments direction”) as to the matters to be taken into account by B in determining the date upon which P shall be deemed to have transferred from A to B in respect of the installation referred to in paragraph (1); and
the date determined by B may be earlier than the date of the notification or the request referred to in paragraph (1)(c).
For the purposes of paragraph (1), a specified event has happened in relation to A if—
A’s electricity supply licence is revoked;
a last resort supply direction is issued due to circumstances having arisen entitling the Authority to revoke A’s electricity supply licence; or
A suffers an insolvency event.
Annotations
Textual amendments
- F1
Pt. 5A inserted (1.7.2013) by The Feed-in Tariffs (Amendment) Order 2013 (S.I. 2013/1099), arts. 1, 5