Article 38H Ongoing obligation to provide quarterly meter readings to the FIT licenseeF1

(1)

The FIT generator or nominated recipient must provide generation meter readings to its FIT licensee for electricity generated by the relevant installation during a quarterly reporting period.

(2)

The FIT generator must provide the generation meter readings within 28 days after the quarterly reporting period.

(3)

The FIT generator or nominated recipient is not entitled to generation payments for electricity generated by the relevant installation during any period that meter readings have not been submitted in accordance with this article.

(4)

When determining the amount of electricity generated by a relevant installation during a certain period (“Period A”) and the periods for which generation meter readings are available do not equate precisely with Period A, the amount of electricity generated during Period A is to be pro-rated by reference to the available meter readings.

Annotations

Textual amendments

F1

Pt. 8A inserted (20.3.2017) by The Feed-in Tariffs (Amendment) Order 2017 (S.I. 2017/131), arts. 1, 8(1)