Part 4 TEMPORARY MANAGEMENT OF PUBLIC RIGHTS OF WAY
| (1) Area | (2) Public right of way | (3) Measure |
|---|---|---|
| City of Doncaster Council | Fenwick-12 between PRoW 03/01 and PRoW 04/01 | Public Right of Way between PRoW 03/01 and PRoW 04/01 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-10 between PRoW 03/02 and PRoW 04/05 | Public Right of Way between PRoW 03/02 and PRoW 04/05 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-14 between PRoW 03/03 and PRoW 06/02 | Public Right of Way between PRoW 03/03 and PRoW 06/02 as shown on Sheets 3 and 6 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-15 between PRoW 03/04 and PRoW 04/07 | Public Right of Way between PRoW 03/04 and PRoW 04/07 as shown on Sheets 3 and 4 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-16 between 03/05 and 03/10 | Public Right of Way between PRoW 03/05 and PRoW 03/10 as shown on Sheet 3 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-11 between PRoW 03/07 and PRoW 03/08 | Public Right of Way between PRoW 03/07 and PRoW 03/08 as shown on Sheet 3 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-11 between PRoW 03/09 and PRoW 05/01 | Public Right of Way between PRoW 03/09 and PRoW 05/01 as shown on Sheets 3 and 5 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-12 between PRoW 04/02 and PRoW 04/03 | Public Right of Way between PRoW 04/02 and PRoW 04/03 as shown on Sheet 4 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-13 between PRoW 04/06 and PRoW 06/03 | Public Right of Way between PRoW 04/06 and PRoW 06/03 as shown on Sheets 4 and 6 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Fenwick-11 between PRoW 05/02 and PRoW 05/03 | Public Right of Way between PRoW 05/02 and PRoW 05/03 as shown on Sheet 5 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Moss-5 between PRoW 05/03 and PRoW 05/04 | Public Right of Way between PRoW 05/03 and PRoW 05/04 as shown on Sheet 5 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Moss-6 between PRoW 06/01 and PRoW 06/02 | Public Right of Way between PRoW 06/01 and PRoW 06/02 as shown on Sheet 6 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Moss-20 between PRoW 07/01 and PRoW 07/02 | Public Right of Way between PRoW 07/01 and PRoW 07/02 as shown on Sheet 7 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Thorpe in Balne-6 between PRoW 08/01 and PRoW 08/02 | Public Right of Way between PRoW 08/01 and PRoW 08/02 as shown on Sheet 8 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Thorpe in Balne-7 between PRoW 08/03 and PRoW 08/04 | Public Right of Way between PRoW 08/03 and PRoW 08/04 as shown on Sheet 8 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Thorpe in Balne-8 between PRoW 09/01 and PRoW 09/02 | Public Right of Way between PRoW 09/01 and PRoW 09/02 as shown on Sheet 9 of the streets, access and rights of way plans to be managed during construction of the authorised development |
| City of Doncaster Council | Thorpe in Balne-13 between PRoW 09/03 and PRoW 09/04 | Public Right of Way between PRoW 09/03 and PRoW 09/04 as shown on Sheet 9 of the streets, access and rights of way plans to be managed during construction of the authorised development |