Regulation 14 Reconsideration of the valuer's determinations

(1)

If the scheme manager is or the Treasury are dissatisfied with the determination notice, either may require the valuer to reconsider the determinations.

(2)

The request must be made within 3 months of the date of the determination notice, set out the reasons for disputing either or both the determinations and be in writing.

(3)

Where the valuer is required to reconsider a determination, the valuer must give the Treasury and the scheme manger notice in writing of their reconsidered determination (“the reconsidered determination notice”).

(4)

The reconsidered determination notice must contain the information specified in regulation 13(6).

(5)

If the scheme manager is or the Treasury are dissatisfied with a reconsidered determination, either may refer it to the Tribunal M1.

(6)

If the Tribunal requires the valuer to redetermine a reconsidered determination, paragraphs (3), (4) and (7) will apply to any re-determination.

(7)

The scheme manager may publish the reconsidered determination notice on the scheme's website or in such other way as the scheme manager thinks fit.

Annotations

Marginal citations

M1

“The Tribunal” means the Upper Tribunal: see section 417(1) of the Act as amended by S.I. 2010/22.