OpenLegislation

Paragraph 24 Offshore safety managementI1

England and Wales

(1)

No stage of the authorised development may commence until the MMO, in consultation with the MCA, has confirmed in writing that the undertaker has taken into account and adequately addressed all MCA recommendations as appropriate to the authorised development contained within MGN654 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” and its annexes.

(2)

No stage of the authorised development may commence until the MMO, in consultation with the MCA, has confirmed in writing that an emergency response co-operation plan has been prepared by the undertaker.

Annotations

Commencement

I1

Sch. 10 para. 24 in force at 8.1.2026, see art. 1