Paragraph 10 I1
No operation of any wind turbine generator forming part of the authorised development may begin until the KIMP has been implemented and completed (where appropriate) for at least three full breeding seasons. For the purposes of this paragraph each breeding season is 1 March to 31 August of each year (inclusive).
Annotations
Commencement
- I1
Sch. 13 Pt. 2 para. 10 in force at 8.1.2026, see art. 1