No offshore works are to commence until the undertaker has confirmed in writing to the Secretary of State that—

(a)

it will make a Marine Recovery Fund Payment wholly in substitution for the guillemot compensation measure and that it has received confirmation from Defra or the Marine Recovery Fund operator that suitable measures are available; or

(b)

it will submit the GCIMP(s) to the Secretary of State for approval.

(2)

If the undertaker confirms that it intends to make a Marine Recovery Fund Payment under sub-paragraph (1)(a) then no offshore works are to commence until the Secretary of State has provided consent in writing to the Marine Recovery Fund Payment being made in substation for the guillemot compensation measure.

(3)

If the undertaker confirms that it intends to submit GCIMP(s) under sub-paragraph (1)(b) then a separate GCIMP must be submitted for each site on which the compensation measure is to be delivered.

Annotations

Commencement

I1

Sch. 13 Pt. 3 para. 2 in force at 8.1.2026, see art. 1