Paragraph 10 Landscape and Ecological Management PlanI1

England and Wales

(1)

No stage of the onshore works may commence until for that stage a written landscape and ecological management plan in accordance with the outline landscape and ecological management plan as appropriate for the relevant stage, has been submitted to and approved by the discharging authority in consultation with the relevant statutory nature conservation body, the Environment Agency, the lead local flood authority, Historic England (where relevant), the Forestry Commission (where relevant), and to the extent that it relates to works seaward of mean high water springs, the MMO.

(2)

The landscape and ecological management plan(s) submitted under sub-paragraph (1) must include an implementation timetable.

(3)

The onshore works must be carried out in accordance with the landscape and ecological management plans approved under sub-section (1), as applicable in each stage.

(4)

Onshore site preparation works must only take place in accordance with the relevant details set out in the outline landscape and ecological management plan as certified in accordance with article 43 (certification of plans, etc.).

Annotations

Commencement

I1

Sch. 2 Pt. 1 para. 10 in force at 8.1.2026, see art. 1