OpenLegislation

Paragraph 19 Reuse of temporary works with the onshore works for North FallsI1

England and Wales

(1)

In the event that any temporary works which have been constructed pursuant to any development consent order that may be made by the Secretary of State in relation to North Falls are proposed to be reused by the undertaker in connection with the authorised development, such reuse must not be commenced until a scheme which accords with sub-paragraph (2) has been submitted to and approved by the discharging authority.

(2)

The scheme to be submitted for approval under sub-paragraph (1) must include details of the temporary works to be reused and a timetable for their reuse and restoration or reinstatement.

(3)

Any scheme approved under sub-paragraph (1) must be implemented as approved.

(4)

Where in the event that any temporary works which have been constructed as part of the onshore works pursuant to this Order are to be subsequently used for the purposes of the construction of North Falls, the undertaker will not be required to maintain, restore or reinstate any such temporary works.

Annotations

Commencement

I1

Sch. 2 Pt. 1 para. 19 in force at 8.1.2026, see art. 1