Paragraph 24 Landfall drilling risk assessmentI1
England and Wales
(1)
No part of Work No. 4 may commence until a landfall drilling environmental risk assessment, in accordance with the approach set out in the code of construction practice, has been submitted to and approved by the discharging authority in consultation with the relevant statutory nature conservation body and the Environment Agency.
(2)
Any control measures identified in the risk assessment submitted under sub-paragraph (1) must be implemented as approved.