Paragraph 7 Traffic and access plansI1
England and Wales
(1)
No stage of the onshore works may be commenced until for that stage the following plans have been submitted to and approved by the discharging authority—
(a)
the construction traffic management plan;
(b)
the workforce travel plan; and
(c)
the public access management plan.
(2)
The plans submitted under sub-paragraph (1) must be in accordance with the outline plans certified under this Order.
(3)
The onshore works must be carried out in accordance with the approved plans as applicable in each stage.
Annotations
Commencement
- I1
Sch. 2 Pt. 1 para. 7 in force at 8.1.2026, see art. 1