Paragraph 3 Further informationI1

England and Wales

(1)

Where an application has been made under paragraph 2 the discharging authority or the relevant planning authority has the right to request such reasonable further information from the undertaker as is necessary to enable it to consider the application.

(2)

If the discharging authority or the relevant planning authority considers further information is needed, and the requirement does not specify that consultation with a requirement consultee is required, it must, within 21 days of receipt of the application, notify the undertaker in writing specifying the further information required.

(3)

If the requirement indicates that consultation must take place with a consultee the discharging authority or the relevant planning authority must issue the consultation to the requirement consultee within five days of receipt of the application. Where the consultee requires further information they must notify the discharging authority or relevant planning authority in writing specifying the further information required within 14 days of receipt of the consultation. The discharging authority or the relevant planning authority must notify the undertaker in writing specifying any further information requested by the consultee within five working days of receipt of such a request.

(4)

In the event that the discharging authority or the relevant planning authority does not give such notification as specified in sub-paragraphs (2) or (3) it is deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.

Annotations

Commencement

I1

Sch. 2 Pt. 2 para. 3 in force at 8.1.2026, see art. 1