OpenLegislation

Paragraph 119 RemediationI1

England and Wales

Where, following the installation of cables forming Work No. 2(c) in relation to the Area of Interest it is identified by the undertaker (who shall notify the PLA as soon as reasonably practicable of this fact, and in any event within 2 business days) or, following inspection by the PLA, it is identified by the PLA (and the same is notified to the undertaker as soon as reasonably practicable), that the level of cable is such that the paragraph 116(a) level has not been achieved or at any time following installation or maintenance the cable has moved such that the requirements of paragraph 116(a) are no longer being achieved, then, unless otherwise agreed in writing with the PLA, the undertaker is required to carry out remediation works as specified in the cable specification and installation plan subject to paragraph 120 in relation to the Deep Water Routes.

Annotations

Commencement

I1

Sch. 9 para. 119 in force at 8.1.2026, see art. 1