Paragraph 25 As built drawingsI1
England and Wales
As soon as reasonably practicable following the completion of the construction of Work Nos. 3 or 4 within plots 01-007, 01-008, 01-010, 01-009 and 02-001, the undertaker must provide to the Agency as-built drawings in a form and scale to be agreed in writing between the undertaker and the Agency (acting reasonably) to show location and depths of the cable ducts as installed which must include identification markings on the sea defence.
Annotations
Commencement
- I1
Sch. 9 para. 25 in force at 8.1.2026, see art. 1