Paragraph 38 I1
England and Wales
Without limiting the other provisions of this Part of this Schedule, the undertaker must make reasonable compensation to the drainage authority from costs and losses which may be reasonably incurred or suffered by the drainage authority by reason of—
any damage to any drainage work;
any raising or lowering of the water table in land adjoining the authorised development or any sewers, drains and watercourses; or
any flooding or increased flooding of any such lands,
caused by the construction of any specified work or any act or omission of the undertaker, its contractors, agents or employees whilst engaged on the specified work.
The drainage authority must take such steps as are reasonable in the circumstances to mitigate in whole or in part and to minimise any costs, expenses, loss, claims, damages, demands, proceedings and penalties to which the indemnity under this paragraph applies where it is within the drainage authority’s reasonable gift and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of the drainage authority’s control. If reasonably requested to do so by the undertaker, the drainage authority must provide a written explanation of how any claim has been mitigated or minimised or where mitigation or minimisation is not possible an explanation as to why.