OpenLegislation

Paragraph 8 I1I2

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

This paragraph provides two approaches for applying for approval required by paragraph 7.

(2)

If the construction work does not require planning permission, the application for approval under paragraph 7 must be made in accordance with paragraph 9.

(3)

If the construction work requires planning permission, the application for approval under paragraph 7 may be—

(a)

made in accordance with paragraph 9, or

(b)

combined with the application for planning permission in accordance with paragraph 10.

(4)

“Planning permission” means planning permission under the Town and Country Planning Act 1990.