Regulation 6 Preparation of EIA reportF1
Where—
pursuant to regulation 4(1)(a), a local authority determines that a proposed scheme or a modified scheme is required to be subject to an environmental impact assessment; or
pursuant to regulation 4(1)(b), a screening opinion given to the local authority states that the scheme is required to be subject to such an assessment,
the local authority must prepare an environmental impact assessment report (referred to in these Regulations as an “EIA report”).
The EIA report must include—
a description of the scheme comprising information on the site, design, size and other relevant features of the scheme;
a description of the likely significant effects of the scheme on the environment;
a description of the features of the scheme and any measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;
a description of the reasonable alternatives studied by the local authority, which are relevant to the scheme and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the scheme on the environment;
a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and
any additional information specified in schedule 2 relevant to the specific characteristics of the scheme or of the type of operations in the scheme in question and to the environmental features likely to be affected.
With a view to avoiding duplication of assessments, account is to be taken of the available results of other relevant assessments in preparing the EIA report.
In order to ensure the completeness and quality of the EIA report—
the local authority must ensure that—
the report is prepared by competent experts; and
it has, or has access to, sufficient expertise to examine the report; and
the report must be accompanied by a statement from the local authority outlining the relevant expertise or qualifications of the competent experts who prepared it.
In order to ensure the completeness and quality of the EIA report, the local authority must where necessary, having regard in particular to current knowledge and methods of assessment, obtain supplementary information about any matter referred to in paragraph (2) which in the opinion of the local authority is directly relevant to reaching a reasoned conclusion on the significant effects of the scheme on the environment.
Where a local authority is required to prepare an EIA report in respect of a modified scheme, the local authority may prepare the report by updating an EIA report previously prepared (if any) in respect of the proposed scheme (without modifications) so as to take account of the proposed modifications.
Annotations
Textual amendments
- F1
Regs. 3-10E substituted for regs. 3-10 (16.5.2017) by The Flood Risk Management (Flood Protection Schemes, Potentially Vulnerable Areas and Local Plan Districts) (Scotland) Amendment Regulations 2017 (S.S.I. 2017/112), regs. 1(1), 3 (with reg. 7)