Section 39 Local flood risk management plans: joint workingI1
Where a local plan district covers more than one local authority's area, the lead authority and the other authorities must, so far as practicable, co-operate with each other with a view to assisting in—
(a)
the preparation of the local flood risk management plan for the district,
(b)
the review of that plan under section 37,
(c)
the preparation of the report published under that section, and
(d)
the preparation of the report published under section 38.
Annotations
Commencement
- I1
S. 39 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.