Subject to the provisions of this Order, the Company or others acting on its behalf may, in the lines and situations and upon the lands delineated on the deposited plans and within the limits of deviation shown on those plans and according to the levels shown on the deposited sections, construct and maintain the works described as follows with all necessary works and conveniences connected with or incidental to them—

  • A concrete wave wall and retaining wall fronting South Quay to the north of the harbour arm commencing at 51°04.6780’N 01°11.3748’E and extending in a north north-easterly direction to 51o04.7395’N 01o11.3970’E and then along a curved path in a northerly direction around to a west south-westerly direction to 51°04.7430’N 01°11.3887’E, together with a rock revetment disposed about a crest line commencing at 51°04.6742’N 01°11.3779’E and extending in a north north-easterly direction to 51°04.7297’N 01°11.3980’E and then along a curved path in a northerly direction around to a west north-westerly direction to 51°04.7331’N 01°11.3949’E. The overall rock revetment extends 19 metres seaward of the crest to its toe and along most of its length extends five metres landward of its crest to the wave wall.

(2)

The Company may, for the purposes of the works authorised by paragraph (1), demolish and remove any structures or apparatus lying within the limits of deviation and may by means of the works, enclose and reclaim so much of the bed of the sea and the foreshore as lies within the limits of deviation and may hold and use the same as part of the undertaking.

(3)

Subject to the provisions of this Order, the Company may, within the limits of deviation, from time to time reconstruct, extend, enlarge, renew, alter, add to, replace or re-lay the works authorised by paragraph (1) and may maintain the same as reconstructed, extended, enlarged, renewed, altered, added to, replaced or re-laid.

(4)

The Company may construct or permit the construction of buildings on the western quay of the Inner Harbour extending above part of the Inner Harbour and on South Quay eastwards of reference point 51°04.7272’N 01°11.2844’E extending above part of the Outer Harbour.