OpenLegislation

Paragraph 11 F1

(1)

Section 27A (determination of certain disputes) has effect as if the disputes mentioned in section 27A(1) included a dispute arising under paragraphs 7 to 9 of this Schedule between a distribution exemption holder and a person requiring a connection in pursuance of paragraph 7(2).

(2)

In the application of section 27A in relation to such a dispute, that section is to be read as if—

(a)

subsection (2) provided that such a dispute, if relating to the connection of any premises to a pipe-line system operated or controlled by a distribution exemption holder, may not be referred to the Authority after the end of the period of 12 months beginning with the time when the connection is made;

(b)

in subsection (5) the references to a gas transporter were to a distribution exemption holder, and the reference to a person requiring a connection to a main of the transporter were to a person requiring a connection in pursuance of paragraph 7(2) of this Schedule;

(c)

subsection (6) and the reference to that subsection in subsection (8) were omitted; and

(d)

the reference in subsection (7) to a dispute arising under section 11(1) were to a dispute arising under paragraph 8(1)(b) or (c) of this Schedule.

(3)

The references in sub-paragraphs (1) and (2)(b) to a person requiring a connection in pursuance of paragraph 7(2) are to be construed in accordance with paragraph 7(5).

Annotations

Textual amendments

F1

Schs. 2AA, 2AB inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 20(3), Sch. 1