Section 19AA ... Revocation of exemptions under section 19AF9F1

F2(1)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F3(2)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(3)

The Authority must revoke an exemption given under section 19A in respect of a facility—

(a)

if the construction of the facility, or (as the case may be) the making of the modification to which the exemption relates, has not been started within the 2 years beginning with the relevant date; or

(b)

if the facility, or (as the case may be) the modification to which the exemption relates, is not operational within the 5 years beginning with the relevant date.

(4)

In subsection (3) “relevant date” means—

(a)

if F4before IP completion day the European Commission notified the Authority that it approved the exemption and terms as copied to it under subsection (1) F5(as it then had effect), the date of that notification;

(b)

if, F6before IP completion day and in accordance with Article 36(9) of the Gas Directive, the European Commission required the Authority to modify the terms, the date of that requirement;

(F7c)

if—

(i)

before IP completion day the Authority sent the European Commission a copy of the exemption and terms under subsection (1) (as it then had effect), and

(ii)

the European Commission does not act as described in paragraph (a) or (b) before IP completion day,

the date 4 months after the Authority sent the European Commission a copy of the exemption and terms under subsection (1) or IP completion day, whichever is the sooner;

(F8d)

if the decision to give the exemption was published under section 19A(11) on or after IP completion day, the date on which the decision was published under section 19A(11).

(5)

The Authority may at any other time revoke an exemption given under section 19A, or modify the terms on which such an exemption is given, in respect of a facility—

(a)

in accordance with the provisions of the exemption; or

(b)

by giving the owner of the facility a notice of revocation at least 4 months before the revocation takes effect.

Annotations

Textual amendments

F1

S. 19AA inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 9

F2

S. 19AA(1) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(3); 2020 c. 1, Sch. 5 para. 1(1)

F3

S. 19AA(2) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(4); 2020 c. 1, Sch. 5 para. 1(1)

F4

Words in s. 19AA(4)(a) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(5)(a)(i) (as amended by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(9)); 2020 c. 1, Sch. 5 para. 1(1)

F5

Words in s. 19AA(4)(a) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(5)(a)(ii); 2020 c. 1, Sch. 5 para. 1(1)

F6

Words in s. 19AA(4)(b) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(5)(b) (as amended by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(9)); 2020 c. 1, Sch. 5 para. 1(1)

F7

S. 19AA(4)(c) substituted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(5)(c) (as amended by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(9)); 2020 c. 1, Sch. 5 para. 1(1)

F8

S. 19AA(4)(d) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(5)(d) (as amended by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 3(9)); 2020 c. 1, Sch. 5 para. 1(1)

F9

Words in s. 19AA heading omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 25(2); 2020 c. 1, Sch. 5 para. 1(1)

Notes on Part I

Modifications

C1

Pt. I: definition of "public gas supplier" applied (E.W.) (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 208(3)(b), 225(2) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)

Pt. I: definition of "public gas supplier" applied (E.W.) (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss. 178, 225(2), Sch. 22 para. 1(4)(e) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)

Pt. I applied (1.3.1996) by 1995 c. 45, s. 6(7); S.I. 1996/218, art. 2

Pt. I applied (1.3.1996) by 1995 c. 45, s. 16(1), Sch. 4 para. 1; S.I. 1996/218, art. 2

Notes on Pipe-line systems, storage facilities and LNG import or export facilities: rights of use etc

Textual amendments

F1

S. 19 cross-heading substituted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 8(1)