If the application relates to the conveyance of gas through pipes to a pipe-line system operated by another public gas transporter (except where that pipe-line system is designed to receive gas at an operating pressure not exceeding 7 bar gauge and the application relates to the conveyance of gas to that system only incidentally to the conveyance of gas to premises in an authorised area), if not already provided for the purpose of any requirement in Schedule 1, a map drawn to an appropriate scale showing the actual or proposed configuration of the pipe-line system the applicant would operate if the application were granted, showing—

(i)

all pipes with a design operating pressure in excess of 7 bar gauge;

(ii)

all pipes effecting connection to the pipe-line system operated by the other public gas transporter; and

(iii)

all points through which it is proposed that gas would be conveyed to the applicant’s pipe-line system wholly or mainly for the purpose of being conveyed to the pipe-line system operated by the other public gas transporter.

Notes on Part III

Footnotes

f1

In paragraphs 1(d), 4 and 6 below, if the application is for an extension of a licence, information and documents need only be given in so far as, in any material respect, they significantly differ from or add to the most recent information or documents which were provided in relation to the same requirement—

  1. (i)

    with an application made by the applicant in accordance with these Regulations; or

  2. (ii)

    subsequent to such an application in pursuance of a condition of the applicant’s licence.