Paragraph 3
A business plan in respect of the activities which would be authorised following the grant of the application, giving estimates, for each of the five years following such grant, of—
the total length of any such pipe-line system (in kilometres);
the total revenue from the activity which would be authorised;
the total capital costs, showing separately such costs in relation to procuring and laying pipe-lines, providing and installing meters, procuring and installing other operational plant and machinery, and overhead and administrative requirements (in all cases excluding finance charges);
the total operating costs, showing separately such costs in relation to fuel (including gas purchases), staff costs, rent and rates, development costs and insurance.
Notes on Part III
Footnotes
- f1
-
In paragraphs 1(d), 4 and 6 below, if the application is for an extension of a licence, information and documents need only be given in so far as, in any material respect, they significantly differ from or add to the most recent information or documents which were provided in relation to the same requirement—
- (i)
with an application made by the applicant in accordance with these Regulations; or
- (ii)
subsequent to such an application in pursuance of a condition of the applicant’s licence.
- (i)