Article 8E CertificationF1
If—
the Authority has asked an applicant or a relevant producer or supplier or related conveyance licensee for information under Article 8C(3) or (4); and
the information has not been supplied by the date specified by the Authority under Article 8C(5),
then the period of 4 months referred to in paragraph (1) shall be extended by the period of delay in supplying such information.
As soon as is reasonably practicable after making the F4... decision under paragraph (1), the Authority must notify the decision and the reasons for it to—
the applicant;
any related conveyance licensee; F5and
the Department; F6...
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Authority must enclose with the notification under paragraph (3) F7(a) or (b) a copy of any report which the Department has prepared under Article 8D in respect of the applicant and which the Authority receives before giving the notification.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Authority must publish its decision to certify or refuse to certify the applicant, together with the reasons for it, in such manner as it considers appropriate.
Annotations
Textual amendments
- F1
Arts. 8B-8L inserted (15.4.2011) by Gas and Electricity (Internal Markets) Regulations (Northern Ireland) 2011 (S.R. 2011/155), reg. 12
- F2
Word in art. 8E(1) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(2)(a) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F3
Word in art. 8E(1) substituted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(2)(b) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F4
Word in art. 8E(3) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(3)(a) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F5
Word in art. 8E(3)(b) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(3)(b) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F6
Art. 8E(3)(d) and word omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(3)(c) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F7
Words in art. 8E(4) substituted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(4) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F8
Art. 8E(5) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(5) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F9
Art. 8E(6) omitted (31.12.2020) by virtue of The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(5) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)
- F10
Art. 8E(7) inserted (31.12.2020) by The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/530), regs. 1(1), 110(6) (with reg. 110(7)(8)) (as amended by S.I. 2020/1016, regs. 1(2), 3(32)); 2020 c. 1, Sch. 5 para. 1(1)