Article 12 Access to worksI1
England and Wales
The undertaker may, for the purposes of the authorised development—
form and lay out the permanent means of access, or improve existing means of access, in the locations specified in Schedule 7 (permanent means of access to works); and
with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.
Annotations
Commencement
- I1
Art. 12 in force at 3.8.2024, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.