Paragraph 150 As built drawingsI1
England and Wales As made
As soon as reasonably practicable following the completion of the construction of the authorised development, the undertaker must provide to the Canal & River Trust as built drawings of any specified works in a form and scale to be agreed between the undertaker and the Canal & River Trust to show the position of those works in relation to the waterway.
Annotations
Commencement
- I1
Sch. 14 para. 150 in force at 3.8.2024, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.