OpenLegislation

Paragraph 215 I1

England and Wales

The plans submitted to Northern Powergrid by the undertaker pursuant to this Part of this Schedule must be sent to Northern Powergrid at [email protected] or such other address as Northern Powergrid may from time to time appoint instead for that purpose and notify the undertaker in writing.

Annotations

Commencement

I1

Sch. 14 para. 215 in force at 3.8.2024, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.