Paragraph 33 I1

England and Wales

(1)

The undertaker must give to Cottam not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 14 days after completion of their construction, must give Cottam written notice of the completion.

(2)

The undertaker is not required to comply with paragraph ‎32 or sub-paragraph ‎(1) in a case of emergency, but in that case it must give to Cottam notice as soon as is reasonably practicable and a plan, section and description of those works as soon as F1reasonably practicable subsequently and must comply with paragraph ‎32 in so far as is reasonably practicable in the circumstances.

Annotations

Textual amendments

F1

Word in Sch. 14 para. 33(2) substituted (28.11.2024) by The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.

Commencement

I1

Sch. 14 para. 33 in force at 3.8.2024, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.