Paragraph 5 Detailed design approvalI1
England and Wales
No part of the authorised development may commence until details of—
the layout;
scale;
proposed finished ground levels;
external appearance;
hard surfacing materials;
vehicular and pedestrian access, parking and circulation areas;
refuse or other storage units, signs and lighting;
drainage, water, power and communications cables and pipelines;
landscaping works, planting works and programme for implementation;
fencing;
security measures; and
any mitigation measures necessary to address noise impacts.
relating to that part have been submitted to and approved in writing by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
The authorised development must be carried out in accordance with the approved details.
Annotations
Textual amendments
- F1
Word in Sch. 2 para. 5(2)(b) inserted (28.11.2024) by The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.
- F2
Sch. 2 para. 5(2)(d) renumbered as Sch. 2 para. 5(2)(c) and the existing Sch. 2 para. 5(2)(c) omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 5 in force at 3.8.2024, see art. 1
Notes on the whole SI
Textual amendments
- F1
Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.