OpenLegislation

Schedule 8 TRAFFIC REGULATION MEASURESI1

England and Wales

(1)

Area

(2)

Extent of temporary traffic signal and banksman control area

B1241 Kexby Lane Eastbound and Westbound Carriageway to facilitate construction of the solar and energy storage parkExtents of traffic signals and banksman control presented on Sheet 1 of the Traffic Regulation Measures Plans
A156 Gainsborough Road Northbound and Southbound Carriageway to facilitate construction of the solar and energy storage parkExtents of traffic signals and banksman control presented on Sheets 4, 5 and 9 of the Traffic Regulation Measures Plans
Clay Lane Eastbound and Westbound Carriageway to facilitate the construction of operation accesses only for the solar and energy storage parkExtents of traffic signals and banksman control presented on Sheet 10 of the Traffic Regulation Measures Plans
Private Means of Access off Marton Road Northbound to facilitate construction of the solar and energy storage parkExtents of traffic signals and banksman control presented on Sheet 7 of the Traffic Regulation Measures Plans
Junction of A1500 Stow Park Road and A156 High Street to facilitate abnormal load access to the solar and energy storage parkExtents of traffic signals and banksman control presented on Sheet 11 of the Traffic Regulation Measures Plans
A1500 Stow Park Road Eastbound and Westbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 11 of the Traffic Regulation Measures Plans
A156 High Street Northbound and Southbound Carriageway adjacent to existing sewage works to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 12 of the Traffic Regulation Measures Plans
A156 High Street Northbound and Southbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 12 of the Traffic Regulation Measures Plans
Headstead Bank Northbound and Southbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 14 of the Traffic Regulation Measures Plans
Cow Pasture Lane Northbound and Southbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 15 of the Traffic Regulation Measures Plans
Cottam Road Eastbound and Westbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 15 of the Traffic Regulation Measures Plans
Torksey Ferry Road Eastbound and Westbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 17 of the Traffic Regulation Measures Plans
Nightleys Road Northbound and Southbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 17 of the Traffic Regulation Measures Plans
Shortleys Road Northbound and Southbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheet 17 of the Traffic Regulation Measures Plans
Torksey Ferry Road Eastbound and Westbound Carriageway to facilitate construction of the cable installation worksExtents of traffic signals and banksman control presented on Sheets 17 and 18 of the Traffic Regulation Measures Plans

Annotations

Commencement

I1

Sch. 8 in force at 3.8.2024, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble omitted (28.11.2024) by virtue of The Gate Burton Energy Park (Correction) Order 2024 (S.I. 2024/1249), art. 1, Sch.