Article 12 Repair and replacement of restorationsI1
England and Wales
Where, on or before 31st March 2006, a relevant dental practitioner has provided a restoration and that restoration requires repair or replacement which he would have been required to repair or replace under paragraph 7 of Schedule 1 to the 1992 Regulations, the succeeding contractor shall repair or replace the restoration in accordance with the terms of the contract giving effect to paragraph 11 of Schedule 3 to the GDS Contracts Regulations or the terms of the agreement giving effect to paragraph 12 of Schedule 3 to the PDS Agreements Regulations.
Annotations
Commencement
- I1
Art. 12 in force at 1.4.2006, see art. 1(1)