Paragraph 4 Notification of commencement and completion of licensed activitiesI1
England, Wales and Scotland
The licence holder must—
notify the MMO local office of the commencement of the first instance of any licensed activity at least 5 working days prior to the commencement of that licensed activity;
notify the MMO local office of the completion of the licensed activities within 10 working days of such completion; and
notify the Source Data Receipt team, UK Hydrographic Office, Taunton, Somerset, TA1 2DN (email: [email protected]) of the completion of the licensed activities within 2 weeks of the date of completion of the licensed activities;
send a copy of the notification required under sub-paragraph (c) to the MMO Marine Licensing Team within 1 week of issue; and
ensure that a notice to mariners is issued at least 10 working days prior to the commencement of the licensed activities, or any part of them, advising of the start date and the expected vessel routes from the local construction ports to the relevant location.
Except in case of emergency, the licence holder must notify the MMO local office of the date of commencement and anticipated duration of any temporary closure of any part of the river Yare under the powers conferred by article 23(2) or (4) (temporary suspension of navigation in connection with the authorised development) of the Order at least 10 working days prior to any such temporary closure.
In sub-paragraph (2) “emergency” has the meaning given to it by article 23(11) of the Order.
Annotations
Commencement
- I1
Sch. 13 para. 4 in force at 15.10.2020, see art. 1