Article 6
In this article and article 7—
-
“major works” means any works on or to the transferred property, being works—
- (a)
of construction, rehabilitation or modernisation; or
- (b)
to rectify major defects due to construction or design;
and
- (a)
-
“final certificate” means the certificate of the architect or other supervisory officer with responsibility for the execution of major works certifying final payment in respect thereof.
Where a contract relating to or in connection with major works—
is subsisting three months after the coming into operation of this order, or
having been entered into after that date is subsisting on the relevant date,
the Council, unless otherwise agreed with the appropriate Borough, shall on or before the date referred to in (a) or the relevant date, as the case may be, notify the Borough that the contract is to be an excluded contract for the purposes of this order.
Article 4 shall not apply to an excluded contract which shall be fulfilled by the Council.
A Borough shall afford the Council, its officers, employees, agents and contractors all such access to the transferred property and rights to use the same as may reasonably be required for the purposes of paragraph (3).
When a final certificate is issued in respect of an excluded contract the Council shall forthwith notify this fact to the appropriate Borough.
Where under a contract for major works entered into before the relevant date a Borough—
makes a payment, the Council shall reimburse the Borough; or
receives a payment, the Borough shall remit the payment to the Council.