OpenLegislation

Article 7

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

Where on the relevant date major works are being carried out directly by the Council, the Council shall complete those works and on doing so shall forthwith notify the appropriate Borough to that effect.

(2)

Any contract in connection with or incidental to works to which paragraph (1) applies which is subsisting on the relevant date shall be an excluded contract for the purposes of this order.

(3)

Article 6(4) shall apply for the purposes of paragraph (1) of this article as it applies for the purposes of paragraph (3) of that article.