Paragraph 19 Soil management

Original text. Later amendments are not shown.

(1)

No part of the authorised development may commence until a soil management plan for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple planning authorities, each of the relevant planning authorities.

(2)

Any soil management plan submitted in accordance with this paragraph must be substantially in accordance with the outline soil management plan as relevant to the activities to which it relates.

(3)

The soil management plan must be implemented as approved.