Regulation 5 Issue and content of CHPGOsI1
Northern Ireland
Where the competent authority—
Receives a request made in accordance with regulation 4(1); and
Is satisfied that the electricity to which the request relates was produced from high-efficiency cogeneration; and
Receives any charge payable under regulation 9;
The authority shall issue a CHPGO in respect of that electricity.
A CHPGO shall be issued to the person making the request for it under Regulation 4(1) or such other person as that person may specify in the request.
A CHPGO—
shall be issued by reference to a standard size of 1MWh; and
shall relate to the net electricity output measured at the station boundary and exported to the grid.
A CHPGO—
shall contain the F2matters set out in Schedule 2 ; and
may contain such other matters as the competent authority considers appropriate.
Where a CHPGO has been issued in respect of any electricity and not revoked, a further CHPGO in respect of the same electricity shall not be issued by the competent authority.
Annotations
Textual amendments
- F1
Reg. 5(2A) inserted (10.12.2014) by The Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration (Amendment) Regulations (Northern Ireland) 2014 (S.R. 2014/284), regs. 1(1), 2(4)(a)
- F2
Words in reg. 5(3)(a) substituted (31.12.2020) by The Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration (Amendment) (EU Exit) Regulations 2018 (S.I. 2018/1206), regs. 1(3), 4(5); 2020 c. 1, Sch. 5 para. 1(1)