OpenLegislation

Paragraph 2 I1

England, Wales and Scotland

In the Districts of North Kesteven and Boston in the County of Lincolnshire, a nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act and associated development under section 115(1)(b) of the 2008 Act.

The nationally significant infrastructure project comprises the following works——

Work No. 1— a ground mounted solar photovoltaic generating station with a gross electrical output capacity of over 50 megawatts including—

(a)

Work No. 1A—

(i)

solar modules;

(ii)

solar stations;

(iii)

inverters;

(iv)

solar module mounting structures; and

(v)

a network of electrical cables; and

(b)

Work No. 1B— electrical cables between solar stations and solar modules within Work No. 1A and connecting Work No. 1A to Work No. 2 and Work No. 4.

Annotations

Commencement

I1

Sch. 1 para. 2 in force at 17.2.2025, see art. 1

Notes on Schedule 1

Textual amendments

F1

Words in Sch. 1 para. 2 substituted (14.4.2025) by The Heckington Fen Solar Park (Correction) Order 2025 (S.I. 2025/482), art. 1(2), Sch.