Paragraph 10 Fencing and other means of enclosureI1
England, Wales and Scotland
No phase of the authorised development may commence until written details of all proposed temporary fences, walls or other means of enclosure, including those set out in the construction environmental management plan, for that phase have been submitted to and approved by the relevant planning authority or, where the phase falls within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities.
No phase of the authorised development may commence until written details of all permanent fences, walls or other means of enclosure for that phase (which must be substantially in accordance with the details within the outline design principles) have been submitted to and approved by the relevant planning authority or, where the phase falls within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities.
Any construction site must remain securely fenced in accordance with the approved details under paragraph (1) at all times during construction of the authorised development.
Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
In the event that temporary fences, walls or other means of enclosure are required for the permitted preliminary works, no permitted preliminary works may take place until written details of all proposed temporary fences, walls or other means of enclosure required for such works have been submitted to and approved by the relevant planning authority or, where the permitted preliminary works fall within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities.