(1)

Prior to the construction of the permissive path, the undertaker must submit details of the permissive path to the county authority for approval, such approval to be in consultation with North Kesteven District Council, such details to cover—

(a)

final routing of the permissive path to be provided, such routing to be substantially in accordance with the routing as shown on the plans contained within the outline landscape ecological management plan;

(b)

the specification of the permissive path; and

(c)

the maintenance regime for the permissive path.

(2)

The permissive path must be provided and open to the public prior to the date of final commissioning in respect of the phase which includes the permissive path.

(3)

The permissive path must be provided and maintained in accordance with the permissive path details and retained until the part of the authorised development in which the permissive path is located is decommissioned pursuant to requirement 18 (decommissioning and restoration).

Annotations

Commencement

I1

Sch. 2 para. 17 in force at 17.2.2025, see art. 1