OpenLegislation

Paragraph 19 Operational Environmental Management PlanI1

England, Wales and Scotland

(1)

Prior to the date of final commissioning for any phase of the authorised development, an operational environmental management plan (which must be substantially in accordance with the outline operational environmental management plan) for that phase must be submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of North Kesteven and the Borough of Boston, both relevant planning authorities.

(2)

The relevant plan submitted pursuant to paragraph (1) must include details of how sheep grazing will be managed and maintained within the fenced areas of the solar park at Work No. 1 throughout the operation of the authorised development.

(3)

The operation of any phase of the authorised development must be carried out and maintained in accordance with the approved operational environmental management plan for that phase.

Annotations

Commencement

I1

Sch. 2 para. 19 in force at 17.2.2025, see art. 1