Paragraph 8 Soil management
No phase of the authorised development may commence until a soil resource management plan for that phase, which must be substantially in accordance with the outline soil resource management plan as relevant to construction activities, has been submitted to and approved by the local planning authority.
All construction works associated with the authorised development must be carried out in accordance with the soil resource management plan submitted and approved pursuant to sub-paragraph (1).
Prior to the date of final commissioning for any phase of the authorised development, a soil resource management plan, which must be substantially in accordance with the outline soil resource management plan as relevant to operational activities, for that phase must be submitted to and approved by the local planning authority.
The operation of the authorised development must be carried out in accordance with the soil resource management plan submitted and approved pursuant to sub-paragraph (3) and maintained throughout the operation of the relevant phase of the authorised development to which the plan relates.
Prior to the commencement of decommissioning works for any phase of the authorised development, a soil resource management plan, which must be substantially in accordance with the outline soil resource management plan as relevant to decommissioning activities, for that phase must be submitted to and approved by the local planning authority.
The decommissioning of the authorised development must be carried out in accordance with the soil resource management plan submitted and approved pursuant to sub-paragraph (5).