Paragraph 9 Battery safety management plan
(1)
Work No. 2 must not commence until a battery safety management plan has been submitted to and approved by the local planning authority in consultation with North Yorkshire Fire and Rescue Service and the Environment Agency.
(2)
The submitted battery safety management plan must either accord with the outline battery safety management plan or detail such changes as the undertaker considers are required to facilitate safety during the construction, operation and decommissioning of Work No. 2 including the transportation of new, used and replacement battery cells both to and from the authorised development.
(3)
The outline battery safety management plan submitted and approved pursuant to sub-paragraph (1) must be implemented as approved.