Paragraph 16 Completion and partial completion of worksI1
England and Wales
Where a completion certificate application by a client has been approved by the regulator, the documents are—
the completion certificate application and any document which accompanied the application, and
the completion certificate.
Where a partial completion certificate application by a client has been approved by the regulator, the documents are—
the partial completion certificate application and any document which accompanied the application, and
the partial completion certificate.
In sub-paragraphs (1) and (2) “completion certificate application” and “partial completion certificate application” have the same meanings as in the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023f1.
Annotations
Commencement
- I1
Sch. 1 para. 16 in force at 16.1.2024, see reg. 1(1)
Footnotes
- f1
-
See regulation 40 (completion certificate applications) and regulation 45 (partial completion applications).