Paragraph 20 Refusal of building assessment certification applicationI1
England and Wales
(1)
Where the regulator has given a notice in relation to a higher-risk building under section 81(3)(b) (building assessment certificates) of the 2022 Act and no more than 7 years have passed since the day that the PAP for the building received it, the document is that notice.
(2)
The document in sub-paragraph (1) is only prescribed for the AP that is also the PAP for the higher-risk building.
Annotations
Commencement
- I1
Sch. 1 para. 20 in force at 16.1.2024, see reg. 1(1)