Paragraph 7
England and Wales
If any dispute arises under paragraph 4, 5 or 6 above as to the materials to be purchased, or the plant to be hired, by the MinisterF1or a strategic highways company from any authority or council, or as to the sums to be paid by any authority or council to the MinisterF2or the company, or by the Ministeror the company to any authority or council, it shall be determined by arbitration.
Annotations
Textual amendments
- F1
Words in Sch. 21 paras. 6-9 inserted (5.3.2015) by Infrastructure Act 2015 (c. 7), s. 57(1), Sch. 1 para. 67(5)(a); S.I. 2015/481, reg. 2(a)
- F2
Words in Sch. 21 paras. 6-9 inserted (5.3.2015) by Infrastructure Act 2015 (c. 7), s. 57(1), Sch. 1 para. 67(5)(b); S.I. 2015/481, reg. 2(a)