Fuel Waste and Storage Fuel Waste and StorageF1
Interim Spent Fuel Store
| Drawing number | Rev | Drawing title | Scale | >Paper size |
|---|---|---|---|---|
| HINK-A2-HHK-00-GP-000 | 01 | Plan | 1:200 | A0 |
| HINK-A2-HHK-00-GE-001 | 01 | North and South Elevations | 1:200 | A0 |
| HINK-A2-HHK-00-GE-002 | 01 | East and West Elevations | 1:200 | A0 |
Access Control Building
| Drawing number | Rev | Drawing title | Scale | >Paper size |
|---|---|---|---|---|
| HINK-A2-HUD-00-GA-001 | 01 | Plans and Elevations | 1:100 | A1 |
Intermediate Level Waste Interim Storage Facility
| Drawing number | Rev | Drawing title | Scale | >Paper size |
|---|---|---|---|---|
| HINK-A2-HHI-00-GA-002 | 01 | Roof Plan and Elevations | 1:200 | A0 |
| HINK-A2-HHI-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Annotations
Textual amendments
- F1
Words in Sch. 1 Pt. 3 substituted (24.3.2018) by The Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2018 (S.I. 2018/413), art. 1, Sch.